Craig & Gould Infrastructure Improvements

Castle Rock Water and the Public Works Department are planning infrastructure improvements in the Craig and Gould North neighborhood to address stormwater flows, upgrade street pavement, and replace aging water and sanitary sewer mains as appropriate. The project will reduce flooding hazards and improve traffic and pedestrian use of the right-of-way. Infrastructure will be upgraded to meet current design criteria standards and will be similar to improvements completed in the Craig and Gould South neighborhood in 2007.

Project scope

With input from residents and considerations from Castle Rock Water, the Public Works Department and the engineering design firm, infrastructure designs have been finalized. View a map of the overall project improvements (PDF).

  • Streets – Existing streets will be reconstructed to current residential design criteria, with the addition of curb and gutter, new asphalt pavement, dedicated on-street parking, signing and striping, and profile grade improvements where feasible. Also, paved sidewalks, crosswalks and ADA compliant ramps will be installed to facilitate pedestrian movement in the neighborhood.
  • Storm Drainage – The neighborhood currently lacks a modern storm drainage collection system, and is susceptible to localized flooding during storm events. A new storm sewer system will be constructed in conjunction with the street improvements to safely and efficiently capture storm flows in the area. An outfall system will then convey these flows along Sixth Street, under the Union Pacific Railroad and connect to the existing storm sewer under Wilcox Street. 
  • Water and Sanitary Sewer – Partial improvements to the existing water mains and sanitary sewer mains in the neighborhood have been implemented in the past as necessary. This project will complete upgrades to the remaining portions of these systems before they become critical, taking advantage of the street and storm sewer construction to minimize inconvenience and disruption to residents.  Water service connections and sanitary sewer laterals will also be replaced where new mains are installed.

Access and disruptions

Road closures and restricted driveway access will be necessary, and street parking will be unavailable within the work zone. Detours for the public will also be necessary, but local access for residents at all times will be a priority. Traffic control plans from the contractor will be approved by the Public Works Department to ensure no disruptions to emergency or other services occur.

Temporary disruptions to water services will occur periodically throughout the project as necessary to the complete the tie-ins for new water mains and service lines. Disruptions to sanitary sewer services will also occur at some properties when individual service lines are connected to the new sanitary sewer mains. To minimize any inconvenience, affected customers will be given advance notice, typically a minimum of 48 hours, when these disruptions are planned. Services will be disrupted for approximately four to six hours, for each effort.  

Please plan to set water aside for drinking and sanitation purposes (for example, fill a bath tub with some water and use a bucket to transfer water to the toilet for flushing) during the temporary water disruptions.  If you notice any air, sediment or discoloration in your waterlines after the shutdown, run cold water from the furthest faucet in the house, and from several faucets, to clear things up.  

Timeline

November 2021 - August 2023 

Contract

AECOM Technical Services, Inc. completed the engineering design, surveying, permitting and geotechnical services for upgrading the streets, alleys, storm drainage, water and sanitary sewer infrastructure. JBS Pipeline, LLC will be the construction contractor.

Cost of the project for design and construction is estimated at $8.7 million. 

Contact

Residents can sign up to receive monthly email updates, or at any time, get additional information, by contacting us at 720-733-6000 or by email.

Construction updates

  1. April 2022 Update:

    Installation of a new water main along Sixth St. between Lewis and Cantril streets, Lewis St. between Fifth and Sixth streets, and Cantril St. between Fifth and Sixth streets is substantially complete. Water main replacement along Cantril St. between Sixth and Front streets is underway.  Expect daytime road closures.  Residents will be notified prior to planned water service disruptions.  

    Replacement of individual water service lines between the water main and meter pits is underway along Gilbert St.  Water service line replacement is expected to begin along Lewis St. between Fifth and Sixth streets in April, followed by Sixth St. between Lewis and Cantril streets, and then Cantril St.  Expect daytime road closures. Residents who will be impacted by brief water shut-offs will be notified in advance via door hangers. 

    Replacement of sanitary sewer service lines along Gilbert St. is scheduled to occur in April.  Expect daytime road closures. No service disruptions are anticipated.    

    Installation of underground storm pipe along Gilbert St. north of Sixth St. is substantially complete.  Storm pipe installation along Sixth St. is underway.  Installation of storm inlets in these areas is scheduled to begin in April.  Expect daytime road closures.                  

    Disruptions in water and restricted road access will typically occur weekdays, between 7 a.m. and 6 p.m.

Craig & Gould stormwater project site map