Current Schedule 

2016 asphalt patching, overlay and reconstruction project

Activity Location Earliest Start Date
Completed
Concrete removal and replacement
Falling Star Place, Paint Pony Circle, Castleton Drive, Castleton Way, Castleton Court, Castleton Road, Genoa Way, Allen Street, Brewer Court, Alexander Place, Front Street, Sunset Drive and Perry Street. April 1
 
Asphalt patching
Falling Star Place, Paint Pony Circle, Castleton Drive, Castleton Way, Castleton Court, Castleton Road, Genoa Way, Allen Street, Brewer Court, Alexander Place, Front Street, Sunset Drive and Perry Street. April 13
 
Overlay Falling Star Place, Paint Pony Circle, Castleton Drive, Castleton Way, Castleton Court, Castleton Road, Genoa Way, Allen Street, Brewer Court, Alexander Place, Front Street, Sunset Drive and Perry Street. April 25  
Asphalt reconstruction
Annabar Drive, Granite Way, Jade Court, Sunstone Lane, and Sunset Drive April 11
 

2016 slurry seal project

Activity Location Earliest Start Date
Completed
Asphalt patching
Sapphire Pointe, Diamond Ridge, Timber Canyon, Liberty Village, Castle Oaks, Fifth Street and and Park Street May 16
 
Slurry seal
Sapphire Pointe, Diamond Ridge, Timber Canyon, Liberty Village, Castle Oaks, Fifth Street and Park Street. June 6  

2016 curb, gutter, sidewalk and miscellaneous concrete projects

Activity Location Earliest Start Date
Completed
Remove and replace curb, gutter, and sidewalk
Sapphire Pointe, Diamond Ridge, Timber Canyon, Liberty Village, Castle Oaks, Fifth Street, Park Street and other various locations throughout Town.
April 11
 

2016 Mikelson Boulevard reconstruction project

Activity Location Earliest Start Date
Completed
Reconstruction Mikelson Boulevard from Enderud Boulevard to Sovereign Street April 11  

2016 concrete pavement restoration project

Activity Location Earliest Start Date
Completed
Concrete pavement panel removal & replacement Front Street, Justice Way and Topeka Way July 5  
Concrete grinding  Front Street, Justice Way and Topeka Way July 18  
Joint sealing Front Street and Topeka Way July 25  

2016 Castle Oaks bridge repair project

Activity Location Earliest Start Date
Completed
Bridge repair
Castle Oaks Drive
Aug. 1 TBD
ConeGuyThank YouSign
We'll be in touch!
While we work to improve roads in your neighborhood, we know it means a temporary inconvenience, so we want you to know what to expect in terms of timing and communication. 

If we will be working on your street, we will send you a letter about two weeks ahead of time, and our contractor will place a note on your door 48 to 72 hours before scheduled work. 

We appreciate your patience. Please know, sometimes, weather impacts our schedule. We will do our best to keep you notified.