Sewer Rehabilitation Project

Castle Rock Water staff identifies sewer pipes for rehabilitation based on a history of root intrusion, increased annual maintenance and pipe defects identified by closed circuit televised (CCTV) inspection. Sewer pipes with capacity issues are also identified as candidates for replacement with larger pipes. Engineering staff develops plans for rehabilitation based on the severity of the defects found.

Cracked sewer pipes can often be repaired from within by pulling a new liner through the sewer pipe. The in-situ method of cured-in-place pipe (CIPP) lining has been in practice since the 1970s and involves pulling a resin-saturated felt tube into the damaged sewer pipe. The tube is then expanded and cured into a new tight-fitting, joint-less pipe within the existing sewer pipe. CIPP lining can extend the service life of sewer pipes by 50-75 years. Rehabilitation by the installation of a CIPP liner, before the sewer pipe deteriorates is cost-effective, and can be completed with minimal disruption to service and results in less future maintenance. 

Severe sewer pipe defects and undersized pipes must be dug-up and exposed in order to complete the repairs. When completed on short sections of pipe, these are referred to as "open-cut point repairs." Sometimes a few critical open-cut point repairs must be completed in advance of CIPP lining a long stretch of sewer pipe. 

Downtown Alley Improvement PrAlley Improvementoject / Jerry Street & Sewer Project

The Town’s 2021-2025 Capital Improvement Program identified multiple streets and alleyways in the downtown area that are to receive upgraded infrastructure. Public Works and Castle Rock Water have identified the present infrastructure is beyond its design life. In advance of street replacement, Castle Rock Water upgraded and replaced appropriate sewer lines and stormwater infrastructure. 

The work at Jerry Street was completed fall 2021 within budget and on schedule. Additional sites are being coordinated. 

Woodlands manhole rehabilitation project

Phase 1Woodlands Manhole Photo 2

From fall 2020 to spring 2021, Castle Rock Water replaced seven manholes on the Woodlands Sewer Interceptor pipeline. The pipeline was constructed over 30 years ago, and the concrete manholes had fully degraded due to corrosive sewer gasses. The contractor installed fiberglass reinforced polymer (FRP) manhole inserts within the existing sewer manholes. The advantage of this rehabilitation method is the majority of the existing concrete manholes were replaced with an FRP manhole in its existing location. This minimized the amount of overall excavation and construction. The end result is all new FRP manholes that are highly resistant to corrosion from sewer gasses.

Phase 2

Scheduled for 2022, as a result of Castle Rock Water staff inspecting and assessing 25 manholes on the interceptor downstream of Phase 1. These manholes are located adjacent to the paved pedestrian trail from Black Pine Drive to Woodlands Boulevard. The condition of these manholes varies from high levels of concrete corrosion with failed existing manhole liners to manholes with lower levels of concrete corrosion. The rehabilitation approach to this phase is anticipated to require a variable approach utilizing different rehabilitation technologies. Staff published a request for proposals in October 2021 and anticipates contracting the project in December. Project construction will occur in 2022.

Woodlands manhole rehabilitation map Phase 2

Past rehabilitation projects

2020Young America neighborhood
2016Castle North neighborhood
2014Castle North and parts of Downtown
2013Glovers neighborhood