Sewer Rehabilitation Project

Castle Rock Water staff identifies sewer pipes for rehabilitation based on a history of root intrusion, increased annual maintenance and pipe defects identified by closed circuit televised (CCTV) inspection. Engineering staff develop plans for rehabilitation based on the severity of the defects found.

Cracked sewer pipes can often be repaired from within by pulling a new liner through the sewer pipe. The in-situ method of cured-in-place pipe (CIPP) lining has been in practice since the 1970's and involves pulling a resin-saturated felt tube into the damaged sewer pipe. The tube is then expanded and cured into a new tight-fitting, jointless pipe within the existing sewer pipe. CIPP lining can extend the service life of sewer pipes by 50-75 years. Rehabilitation by the installation of a CIPP liner, before the sewer pipe deteriorates to a failed condition that might require a street-cut to repair, is cost-effective, and can be completed with minimal disruption to service and results in less future maintenance.  

Severe defects often must be dug-up and exposed in order to complete the repairs. When completed on short sections of pipe, these are referred to as "point repairs". Sometimes a few critical point repairs must be completed in advance of CIPP lining a long stretch of sewer pipe.  

In 2016, Castle Rock Water is rehabilitating clay pipes in the Castle North neighborhood. The sewer pipes in this neighborhood were installed in the early 1970's and are exhibiting severe cracking, joint separation and root intrusion. In 2014, point repairs were completed on some of the worst sections of pipe. The Town is now contracting with Insituform Technologies to complete CIPP lining of nearly two miles of pipe in the neighborhood at a contract price of $215,590. The project is anticipated to begin in October 2016, with completion scheduled for February 2017.

A project to rehabilitate a number of manholes around Town is also anticipated to begin in 2016 or early 2017.  

Accomplishments


During 2014, the Castle North neighborhood and several pipes in the Downtown area were the focus of a sewer rehabilitation project to complete point repairs of broken or damaged sewer pipes. Point repairs were completed at twenty different locations. The project was completed by local contractor 53 Corporation at a contract price of $172,000.

In 2013, almost two miles of old clay sewer pipe in the Glovers neighborhood was rehabilitated with CIPP lining.  The 2013 project was completed by Layne Inliner, LLC on time and under budget at a cost of $275,000.

During 2012, a high priority sewer project was completed and several emergency sewer repairs were made. An old 1930's era failing sewer pipe under the railroad tracks at Seventh St. and the old Front St. was replaced. The project involved the bored installation of 120 linear feet of 20-inch diameter steel pipe, followed by the installation of 140 linear feet of new 8-inch PVC sewer pipe and three new manholes. The project required securing a license agreement with the railroad for the new installation. Total project cost was $120,000. Emergency repairs were made at Sixth and Wilcox streets in the Downtown area and near Parson’s Way in Founders, at a cost of almost $15,000.

Program cost


The actual cost of this program varies from year-to-year, but $350,000 is budgeted annually.

More information

Residents are advised to contact Castle Rock Water with any concerns or questions.