Import

Imported supplies
While securing local water rights and conserving existing water supplies is important, the Town's plan also includes looking at opportunities to partner with others in our region to further secure the community’s water future. The Legacy Water Projects in particular are the WISE and the Box Elder projects. They are also known as the alternate source of supply projects. These projects are designed to import water from Denver, Aurora, and other water rights the Town is purchasing on the South Platte River north of Denver.
Import
Alternate source of water supply
In October 2012, Town Council voted in favor of pursuing a hybrid solution for the Town's long-term water goals. Town staff entered into negotiations with Stillwater Resources and WISE partnership, which could result in renewable water being imported into the Town as soon as 2017. For more information about this process, view a timeline of this process or past Town Council meetings.

South Metro Water Supply Authority
This authority has been instrumental in developing opportunities for smaller Front Range water providers to partner with larger ones, such as Denver and Aurora. The authority also has been implementing studies and projects as identified in the Regional Water Master Plan.
 
WISE Partnership
In 2009, Castle Rock Water became part of the WISE Partnership. That partnership of ten South Metro organizations has signed agreements to import renewable water from Denver and Aurora. To date, the Town has invested approximately $5.3 million into a pipe big enough for a man to walk through (the Western Pipeline) that runs approximately 20 miles along E-470. This pipe is a critical piece of the system that will not only allow us to import WISE water but also water from the Box Elder project. 

Additional large pipelines, pumps and tanks will need to be constructed in the next two to three years, from E-470 to Rueter-Hess Reservoir and from Rueter-Hess Reservoir to the Town, in order to ensure that WISE water can arrive in the Town by 2017. These same pipeline investments of an estimated $23 million will also be a key part of the Box Elder project carrying that water to the Town in the future. 

WISE local infrastructure


Several South Metro Authority members are currently working on a project to design and construct a water pipeline from E-470 and Peoria Street / Chambers Road south towards Rueter-Hess Reservoir and Water Treatment Plant. 

Box Elder project


For the Box Elder project, Castle Rock Water has invested about $5.7 million dollars into water rights in the South Platte River north of Denver in Weld County. That’s about 1/3 of the total water rights targeted for purchase in the project. The Town has an option on a well field in Weld County that could be used to divert these water rights. First, the Town must secure the remaining water rights needed to make the well field economical. 

Securing these water rights will be a focus in the next several years. Many of the details of the Box Elder project are still in the planning stage, but the goal is to bring water from this project to Town sometime after the year 2025. 

Both of the Legacy Water Projects are important to the community and have become a good fit into Castle Rock Water’s overall long-term water puzzle.

East Cherry Creek Valley Water and Sanitation District Northern Pipeline
An agreement to purchase capacity in the northern pipeline has been negotiated and is available to all South Metro Water Supply Authority members. The Town is planning to purchase additional capacity in this pipeline and is actively negotiating directly with the authority members and East Cherry Creek Valley Water and Sanitation District (ECCV) on the final share of the pipe's capacity and cost. 

WISE infrastructure construction


As Castle Rock Water works to secure the community's long-term water plan, the WISE project continues to make progress. Various pieces of the local infrastructure are either in the design phase or ready to be designed. The total WISE expenditures to date are $6.34 million. Over the next five years, a total spending of $24.7 million is expected. Pipeline project updates are available below. The purpose of this pipeline project is to import water from the existing WISE / Box Elder Pipeline to the Ray Waterman Treatment Plant.
WISE pipeline status map
Ridgegate Pipeline (blue)
The design of the pipeline and Rueter-Hess Water Treatment Facility upgrades is complete. Construction bids that were received in mid-March 2016 are being evaluated. Construction is expected to start in the summer. 

Existing Parker Water and Sanitation District Pipeline
(pink) 
Castle Rock Water partnered with Parker Water and Sanitation District on a study of the hydraulics of the WISE water flow. The study is complete and discussions regarding additional infrastructure design / construction have begun with Parker Water and Sanitation District. 

Canyons North Line (red)
The developer of the Canyons Development reported they are committed to being a partner on a portion of the local infrastructure that would convey WISE water from Parker Water and Sanitation District's existing infrastructure near Rueter-Hess Reservoir to the Town. The design-build contract is out to bid with construction set to begin later this year. 

Pipeline to Ray Waterman Water Treatment Plant
(green)
The design of the final leg of the local infrastructure is 30 percent complete. The topographical survey and cultural resource / environmental survey for the project are complete. The consultant will begin work on the geotechnical and utility investigations soon. Property easement agreements and acquisition for the five-mile corridor are nearly complete.  
Existing WISE / Box Elder Pipeline (pink - top of map)
The Western Pipeline modifications are approximately 50 percent complete. Substantial completion is scheduled for November 2016. There have not been any change orders to date. 

The design of the Quebec Street Water Treatment Plant is 100 percent complete and construction has begun. The necessary tie-ins are complete and underground piping work including disinfection and pressure testing will be complete in March 2016. 

The Smoky Hill Tank as shown in the photo to the right is complete with exception of the aesthetics which will be added in spring 2016. Underground piping connections were made in February 2016. The site is prepared for final site grading to occur spring 2016.
Smoky Hill